Planning benchmark for a medium-quality building in and around Dhaka: about Tk 1,800–2,000 per sq ft on good soil and Tk 2,500–3,000 per sq ft on piles, before VAT, income tax and contractor profit.
Materials cost more in 2026: 60-grade rod was Tk 92,500–94,500 per tonne in September and cement Tk 490–550 per bag in May. At typical consumption, that adds only about Tk 40 per sq ft over mid-2025.
Soil matters more than the price of rod. On these benchmarks, piles instead of a shallow foundation can add Tk 700–1,000 per sq ft across every floor.
Contractor margin, lifts, a basement, generator, substation, design, approvals and utilities push the all-in figure well above the headline rate. Ask for each as a separate line.
A soil test and a full structural design to BNBC 2020 cost little compared with the money they protect.
What does the per square foot construction cost include?
When a contractor says "Tk 2,500 per square feet", ask what that covers. The rate is normally applied to the total floor area of all storeys and covers the building itself: foundation, frame, walls, plaster, floors, doors, windows, wiring and plumbing.
Grey structure vs finished building
A grey structure quote covers the foundation, columns, beams, slabs, stairs and usually the brick walls, but not plaster, tiles, paint, doors, fittings or services. A finished (turnkey) rate includes those. Comparing one with the other is a common budgeting mistake.
What the rate usually leaves out
Land, registration and mutation
Architectural, structural and MEP design and site supervision fees
Soil test (BUET's April 2026 rate for one borehole up to 20 m in Dhaka is Tk 80,000)
Approval fees (RAJUK, CDA, municipality or building committee)
Electricity, water, gas and sewer connections
Lift, generator, substation, fire pump and water reservoir
Basement, boundary wall, gate, drainage and site filling
Interiors, kitchen cabinets and air-conditioners
VAT, advance income tax and the contractor's profit
Building construction cost in Bangladesh per square foot (2026)
The clearest public benchmark is a July 2025 Prothom Alo article by the chief engineer of Narayanganj City Corporation. It gives preliminary rates for medium-quality buildings in and around Dhaka, excluding VAT, income tax and contractor profit:
Good soil, shallow foundation: about Tk 1,800–2,000 per sq ft
Weak soil, pile foundation: about Tk 2,500–3,000 per sq ft
His 10-storey example (medium quality, 12,000 sq ft plinth, piles): about Tk 30–36 crore
Prices have moved since. Using the rod and cement consumption implied by REHAB's costing (explained below), the rise from mid-2025 to September 2026 adds roughly Tk 40 per sq ft. Soil, finishes and services move the total far more.
High-specification and commercial buildings
For an upper reference point, in April 2026 the housing ministry put the cost of the proposed 21-storey Secretariat tower at about Tk 3,500 per sq ft, excluding basements, VAT, income tax and profit. The four basement levels added about Tk 760 per sq ft on top. That building was planned with central air-conditioning, 14 lifts, low-E glass and automated fire protection.
Services push commercial buildings up. In the same project, the 2,400-ton air-conditioning system was budgeted at Tk 60 crore, the 14 lifts at Tk 31 crore, fire detection and protection at Tk 13.3 crore and five generators at about Tk 5.35 crore. Offices, shops and clinics also carry heavier loads and longer spans than homes.
Dhaka vs district towns vs village
Rod and cement are sold under national brands, so prices differ mainly by transport. Labour is where location shows. The government day-labour rate since July 2025 is Tk 800 in the Dhaka and Chattogram city corporations, Tk 750 in divisional towns and other city corporations, and Tk 700 in districts and upazilas.
A village build saves on labour but often spends more on raising the plinth above flood level, filling earth and carrying materials. Outside development authorities, city corporations and municipalities, upazila building committees now approve plans up to seven storeys and district committees above that, checking compliance with BNBC 2020.
Construction material prices in Bangladesh, October 2026
Prices change month to month, so check them the week you buy. The latest reported figures:
MS rod, 60-grade (TCB retail): Tk 92,500–94,500 per tonne in early September 2026, up from Tk 88,000–92,000 a month earlier. In March 2026, leading brands of 75-grade rod reached Tk 91,000–95,000 per tonne at the mill gate after a jump of about Tk 10,000 in ten days.
Cement: Tk 490–550 per 50 kg bag in May 2026, after the Middle East conflict pushed up clinker and freight costs.
Bricks: Tk 10–15 per piece depending on quality (July 2025). A concrete hollow block, about four times the size of a brick, was Tk 50 (January 2025).
Stone chips: Tk 165–215 per cft at Dhaka retailers (July 2025).
Sand: Sylhet sand sold for Tk 105 per cft in Khulna in March 2026. Local filling sand is far cheaper.
Labour: the government day-labour rate is Tk 700–800 a day. Skilled masons, rod binders and shuttering crews cost more, and many builders agree labour as a rate per sq ft.
Rod and cement depend on imported scrap and clinker, shipping and the dollar. Industrial electricity tariffs also rose 17.86 percent in June 2026, which raised steel mills' costs.
How material prices feed into your per sq ft cost
When REHAB costed the 2022 price spike, a Tk 22,000 per tonne rise in rod added Tk 100 per sq ft, and a Tk 85 per bag rise in cement added Tk 30 per sq ft. That implies roughly 4.5 kg of rod and 0.35 bag of cement per sq ft of floor area in a typical apartment building. In practice:
Every Tk 10,000 per tonne change in rod moves your cost by about Tk 45 per sq ft.
Every Tk 50 per bag change in cement moves it by about Tk 18 per sq ft.
At 2026 prices, rod and cement together come to about Tk 600 per sq ft. That is roughly a fifth to a third of the benchmark rates above.
These are averages: your structural design sets the real quantities.
Foundation cost: shallow vs pile, and why soil decides
The same building can cost very different amounts depending on what lies under it. On firm ground, footings or a raft may be enough. On soft or recently filled land, the columns may need piles, and their length depends on how deep the firm layer is.
The benchmark rates show what is at stake. Moving from Tk 1,800–2,000 to Tk 2,500–3,000 per sq ft means Tk 700–1,000 more per sq ft over the whole building, or roughly Tk 70 lakh to Tk 1 crore on 10,000 sq ft. Only a soil test tells you which case you are in, and three boreholes cost a tiny fraction of that. Read our soil test guide before you sign a contract.
Basements and other sub-structure
A basement needs retaining walls, shoring, dewatering, waterproofing and protection for neighbouring buildings, so it costs much more per sq ft than an upper floor. Price it separately, with your structural engineer's input on depth, groundwater and the adjoining plots.
Lift, generator, substation and fire systems: the big add-ons
In April 2026, one local brand listed its lifts at Tk 15 lakh to Tk 1 crore, and a 14-person model was listed on a retail site at about Tk 22 lakh. Add the shaft, pit, installation and an annual maintenance contract.
Size the generator from the electrical load calculation; backing up only lifts, pumps and stair lights costs far less than backing up the whole building. Buildings with a higher electrical demand may need their own substation, with space on the ground floor or in the basement. The power utility sets the threshold, so your MEP engineer should check it at design stage.
Under BNBC 2020, a building of ten storeys or 33 metres and above is classed as multi-storey, which brings extra requirements; for example, a diploma engineer's site supervision must be countersigned by a graduate engineer. Taller and commercial buildings also need fire detection, hydrants and, depending on use and height, sprinklers, a fire pump and protected stairs. Budget for these from the start rather than adding them for an approval.
Want a realistic budget before you commit? Call our architects and engineers on +880 1823-017070, email sthapatto@gmail.com or start your project online.
Worked examples: house and building construction cost in Bangladesh
These examples are illustrative, not quotes. They use the July 2025 benchmark rates, add about Tk 40 per sq ft for 2026 material prices and assume contractor margin plus taxes of 10–15 percent. Your plot, soil, design and finishes will change every number.
5-storey building cost on 5 katha (Dhaka, pile foundation)
Assumptions: 5 katha = 3,600 sq ft of land; about 2,200 sq ft per floor (your FAR and setbacks decide the real figure); five floors including ground-floor parking = 11,000 sq ft; medium finishes; one lift.
Building at Tk 2,500–3,000 per sq ft: Tk 2.75–3.30 crore
2026 material adjustment: about Tk 4.4 lakh
Contractor margin and taxes (10–15 percent): Tk 28–50 lakh
One mid-range lift (assumed from listed prices): Tk 15–25 lakh
Indicative total: about Tk 3.2–4.1 crore (Tk 32–41 million), or roughly Tk 2,900–3,700 per sq ft
If the soil test allows a shallow foundation, the building line falls to Tk 1.98–2.20 crore, a saving of Tk 77 lakh to Tk 1.1 crore.
6-storey building cost on 3 katha
Assumptions: 3 katha = 2,160 sq ft; about 1,300 sq ft per floor; six floors = 7,800 sq ft; pile foundation; one lift.
Building at Tk 2,500–3,000 per sq ft: Tk 1.95–2.34 crore
Material adjustment: about Tk 3 lakh
Contractor margin and taxes: Tk 20–35 lakh
One lift: Tk 15–25 lakh
Indicative total: about Tk 2.3–3.0 crore, or Tk 3,000–3,800 per sq ft. On a small building, the lift weighs more per sq ft.
Duplex house construction cost (2,400 sq ft)
Assumptions: two floors of 1,200 sq ft; good soil and a shallow foundation; medium finishes; no lift.
Building at Tk 1,800–2,000 per sq ft: Tk 43.2–48 lakh
Material adjustment: about Tk 1 lakh
Contractor margin and taxes: Tk 4.3–7.2 lakh
Indicative total: about Tk 48–56 lakh
Better finishes, a boundary wall, gate, septic tank and interiors come on top; price them item by item. If the soil needs piles, the building line alone rises to Tk 60–72 lakh. See our duplex house design guide.
10-storey building cost with pile foundation and basement
Assumptions: 10 katha plot (7,200 sq ft) where your FAR allows ten storeys; about 4,300 sq ft per floor = 43,000 sq ft; one basement of about 6,000 sq ft; two lifts. For illustration only, we price the basement at about double the floor rate.
Above-ground building at Tk 2,500–3,000 per sq ft: Tk 10.75–12.90 crore
Basement at an assumed Tk 5,000–6,000 per sq ft: Tk 3.0–3.6 crore
Material adjustment: about Tk 20 lakh
Contractor margin and taxes: Tk 1.4–2.5 crore
Two lifts: Tk 30–50 lakh
Indicative total: about Tk 15.7–19.7 crore, before generator, substation, fire pump, design, approvals and utilities
Building construction cost calculator for Bangladesh: 7 steps
Find your total floor area. Your plot size, road width and FAR set how much you can build; our RAJUK FAR guide explains the calculation.
Pick a base rate: Tk 1,800–2,000 per sq ft on good soil or Tk 2,500–3,000 on piles for medium quality. Use the low end only if your design is simple.
Adjust for today's prices: add about Tk 45 per sq ft for every Tk 10,000 per tonne rod has risen since mid-2025, and about Tk 18 for every Tk 50 per bag on cement.
Multiply floor area by the adjusted rate.
Add the basement, lifts, generator, substation and fire system as separate lines.
Add the contractor's margin and taxes, then design fees, soil test, approval fees and utility connections.
Add a contingency you control, not one inside the contractor's price.
10 ways to control construction cost without compromising safety
Do the soil test before design. It decides between footings and piles, which is the biggest swing in the budget.
Get a full structural design to BNBC 2020. It is safe without being over-designed, and nobody has to guess rod sizes on site.
Keep the plan simple. A regular column grid and stacked bathrooms and kitchens save formwork and transfer beams.
Finish the drawings before construction starts. Changes on site cost far more than changes on paper.
Buy branded rod and cement in planned lots and check weights and test certificates.
Spend on what is hard to change later, such as waterproofing, wiring and plumbing; save on items you can upgrade later.
Consider concrete hollow blocks for partition walls. The government has announced plans to phase out clay bricks in favour of blocks, and lighter walls reduce the load on the frame.
Design the foundation for the final number of floors if you plan to build in phases. Never add storeys to a foundation that was not designed for them.
Coordinate MEP early, so conduits and pipes go in before concrete is cast.
Test as you build. At BUET's 2026 rates, a set of three concrete cylinders costs Tk 4,500 to test and three rod samples Tk 2,500, which is very little compared with rework.
Red flags in contractor quotes
A single per sq ft figure with no bill of quantities, specifications or brands.
Rod quantity offered as "kg per sq ft" instead of being taken from structural drawings.
No concrete mix or strength stated, and no cylinder or rod tests.
Foundation, piling, earthwork, MEP or VAT quietly left out.
A price far below the others. Poor bricks alone can mean 50–100 extra bricks per thousand.
Advice to skip the soil test or the engineer, or to "save" by shrinking columns or rods.
A rod grade different from the structural drawings. A BUET civil engineering professor notes that BNBC 2020 generally limits main bars in beams, columns and shear walls to 400–420 grade, allowing higher grades in slabs.
Large advances, no payment schedule, no retention and no clause for rod and cement price changes.
Why design and engineering save money
Most overruns start before the first column is cast: an unclear brief, uncoordinated drawings or a structure designed by guesswork. Coordinated architectural, structural and MEP drawings let contractors price the same scope, so you can compare like with like.
Approvals now depend on it too. Under the new Dhaka building rules introduced in December 2025, structural, electrical and mechanical designs must be submitted for approval along with the architectural design. An occupancy certificate is needed before you can get electricity and water connections. Approval fees are rising several-fold as well. The proposal reported in December 2025 set residential fees at Tk 50 per square metre, about Tk 1.5 lakh for a 3,000 square metre building. Confirm the current schedule with RAJUK and see our building approval guide.
How Sthapatto Angon can help
Sthapatto Angon is an architecture and engineering design consultancy in Lalmatia, Dhaka, established in 2013. Our architects work with in-house structural and MEP engineers, so decisions about soil, structure and services are made together, on paper, before you spend on site.
Plot and FAR study, so you know how much you can build before you price it
Structural design in RCC, steel or composite to BNBC 2020, coordinated with MEP design
Coordinated drawings and specifications that contractors can price on the same basis
Approval drawings, plus project management, contractor coordination and quality control for our designs
Our residential work includes nine-storey buildings at Jolshiri Abashon in Dhaka (one completed in 2023), a 2,400 sq ft two-storey residence at Sitakunda, Chattogram (completed 2021), and a 10-storey, 32,000 sq ft mixed-use building in Gaibandha Sadar, now under construction.
Frequently asked questions
What is the construction cost per square feet in Bangladesh in 2026?
For a medium-quality RCC building, plan on about Tk 1,800–2,000 per sq ft on good soil and Tk 2,500–3,000 per sq ft with piles, plus about Tk 40 for 2026 material prices. Those rates exclude VAT, tax and contractor profit. Lifts, basements, premium finishes and soft costs come on top.
How much does it cost to build a 5 storey building in Bangladesh?
A 5-storey building of about 11,000 sq ft on 5 katha in Dhaka, with piles and one lift, comes to roughly Tk 3.2–4.1 crore in our illustrative example, including contractor margin and taxes. A shallow foundation could cut up to about Tk 1 crore. Design, approvals, utilities and interiors are extra.
What is the construction cost of a 6 storey building on 3 katha land?
With about 1,300 sq ft per floor, piles and one lift, our worked example gives roughly Tk 2.3–3.0 crore. Confirm your permitted floor area and soil conditions before you budget.
How much does a duplex house cost to build in Bangladesh?
A 2,400 sq ft duplex with medium finishes on good soil comes to about Tk 48–56 lakh in our example, including contractor margin and taxes. Better finishes, a boundary wall and interiors add to that, and piles can raise the building cost to Tk 60–72 lakh.
How much rod and cement are needed per square foot?
REHAB's 2022 costing implies roughly 4.5 kg of rod and 0.35 bag of cement per sq ft of floor area in a typical apartment building, about Tk 600 per sq ft at 2026 prices. Your structural drawings, not a rule of thumb, should set the actual quantities.
Is building construction cheaper outside Dhaka?
Somewhat. The government day-labour rate is Tk 700 in districts and upazilas against Tk 800 in Dhaka, but rod and cement cost about the same everywhere. Transport, raised plinths and earth filling can cancel the savings in rural areas.
Does the per sq ft rate include design, soil test and approval costs?
Usually not. Ask every contractor to list design, soil test, approval fees, utility connections, VAT and profit separately, so you can compare quotes on the same basis.
২০২৬ সালে বাংলাদেশে বাড়ি নির্মাণ খরচ মাঝারি মানের আরসিসি ভবনে প্রতি বর্গফুটে মোটামুটি ১,৮০০–২,০০০ টাকা (ভালো মাটি, শ্যালো ফাউন্ডেশন) এবং দুর্বল মাটিতে পাইল লাগলে ২,৫০০–৩,০০০ টাকা ধরা যায়। এই হিসাবে ভ্যাট, আয়কর ও ঠিকাদারের মুনাফা ধরা নেই। সেপ্টেম্বর ২০২৬-এ ৬০ গ্রেড রড টনপ্রতি ৯২,৫০০–৯৪,৫০০ টাকা এবং মে ২০২৬-এ সিমেন্ট বস্তাপ্রতি ৪৯০–৫৫০ টাকা ছিল। লিফট, বেসমেন্ট, জেনারেটর, সাবস্টেশন, ডিজাইন ফি, অনুমোদন ও ইউটিলিটি সংযোগের খরচ আলাদা যোগ করতে হবে। উদাহরণ হিসেবে, ৫ কাঠায় পাইল ফাউন্ডেশন ও একটি লিফটসহ প্রায় ১১,০০০ বর্গফুটের ৫ তলা ভবনে আনুমানিক ৩.২–৪.১ কোটি টাকা লাগতে পারে। নিজে হিসাব করতে মোট ফ্লোর এরিয়াকে প্রতি বর্গফুটের রেট দিয়ে গুণ করুন, তারপর বেসমেন্ট, লিফট, ঠিকাদারের মুনাফা ও কর, ডিজাইন ও অনুমোদনের খরচ এবং একটি কন্টিনজেন্সি যোগ করুন। সবচেয়ে বড় সাশ্রয় আসে আগেভাগে মাটি পরীক্ষা এবং বিএনবিসি ২০২০ অনুযায়ী পূর্ণাঙ্গ স্ট্রাকচারাল ডিজাইন থেকে। নির্মাণসামগ্রীর দাম প্রতি মাসে বদলায়, তাই কেনার আগে হালনাগাদ দর জেনে নিন। পরামর্শের জন্য ফোন করুন ০১৮২৩-০১৭০৭০।
Ready to plan your building?
Send us your plot size, location and what you want to build, and we will help you turn it into a design and a budget you can trust. Call +880 1823-017070, email sthapatto@gmail.com or start your project online.
Prothom Alo (27 July 2025): How much does a 10-storey building cost? (in Bangla)
BSS (5 April 2026): Ministry refutes report on cost of 21-storey Secretariat building
Prothom Alo English (5 April 2026): 21-storey building planned at secretariat, questions raised over cost
The Daily Star (3 September 2026): Steelmakers squeezed by higher costs, weak demand
The Business Standard (12 March 2026): Rod prices jump Tk10,000 per tonne in 10 days, cement up Tk25 per bag
The Financial Express (16 May 2026): Higher freight charges raise cement production cost
The Daily Star Bangla (3 August 2025): Rod prices at a three-year low as demand falls (in Bangla)
Prothom Alo (27 July 2025): Retail prices of building materials (in Bangla)
The Daily Star (22 January 2025): Bangladesh must switch to hollow blocks to reduce pollution
The Business Standard (18 October 2023): How substandard bricks affect construction quality, drive up costs
Dainik Purbanchal, Khulna (12 March 2026): Rod, cement, sand and stone prices raised at will (in Bangla)
The Financial Express (23 May 2025): Daily wage for labourers in government jobs rises by Tk 225
The Daily Star (29 March 2022): Why are apartment prices going through the roof?
BUET Department of Civil Engineering, BRTC (effective April 2026): Approved rates for testing of materials and services
Prothom Alo (31 August 2025): What to check when buying rod for construction, by Dr Khan Mahmud Amanat, BUET (in Bangla)
The Business Standard (25 February 2021): Updated National Building Code comes into effect
Independent Television (9 March 2026): New Dhaka building rules: no electricity or water connection without an occupancy certificate (in Bangla)
Prothom Alo English (2 December 2025): Dhaka building construction to rise as rules set to take effect
UNB (27 June 2026): District, upazila building construction committees formed to regulate building approvals outside urban authorities
This article is general information, not legal or financial advice. Construction costs and material prices change every month and the figures here are indicative as of the dates shown. Get current written quotes, and confirm approval rules and fees with RAJUK or your local authority and a qualified architect or engineer before you commit.