Building Approval in Dhaka: RAJUK, BNBC 2020 and What Your Architect Prepares

By the Sthapatto Angon design team, Dhaka. Updated October 2026.

In the RAJUK area, most new buildings now follow the steps set by the Dhaka Metropolitan Building Rules 2025: a planning permit for the plot (formerly called land use clearance), a construction permit based on drawings that follow the 2025 rules and the Bangladesh National Building Code (BNBC 2020), extra review for large, tall or special buildings, a notice to RAJUK before work starts, construction according to the approved plan, and an occupancy certificate before the building is used. Outside Dhaka, the same work is done by other development authorities, city corporations or municipalities.

Dhaka's rules changed recently: the Dhaka Metropolitan Building Rules 2025 replaced the 2008 rules in December 2025, and the Detailed Area Plan (DAP) was amended in December 2025 and again in October 2026. Use this guide to understand the process, then confirm the current requirements with RAJUK or your local authority before you apply.

Who approves buildings where

Step 1. Planning permit (formerly land use clearance)

Before any drawings are approved, RAJUK checks whether the use you plan (residential, commercial, industrial, institutional and so on) is allowed on your plot under the Detailed Area Plan (DAP). Under the 2025 rules this first approval is called a planning permit; older documents and some RAJUK forms still call it land use clearance (LUC). You apply with the land documents and a survey map, RAJUK inspects the site, and the permit it issues is valid for a limited time.

Step 2. Construction permit

With the planning permit in hand, your architect prepares the construction permit drawings and applies through RAJUK's online Electronic Construction Permitting System (ECPS). A typical submission includes:

In 2019 the government cut the number of clearances a typical building needs from 16 to four: the land use clearance (now the planning permit), an NOC from the Civil Aviation Authority where the site lies under flight paths, an NOC from law enforcement agencies for buildings near key point installations, and a Fire Service NOC for taller buildings. Applications are now made online through ECPS.

Step 3. Large, tall and special buildings

Large developments and special projects go through RAJUK's separate large and special project (LSP) review before a construction permit is issued. Under BNBC 2020, a building of ten storeys or 33 metres and above counts as multi-storey, which brings stricter fire safety and structural requirements. Factories also need environmental clearance from the Department of Environment and layout approval from DIFE; our factory planning guide explains those steps.

Step 4. Build to the approved plan

Before any work starts on site, including excavation or piling, notify RAJUK through ECPS (the construction start notice). Construction must then follow the approved drawings, under the supervision of qualified professionals. Any change to the number of floors, the footprint or the use needs a revised approval first. Building beyond the approved plan can lead to penalties or demolition orders.

Step 5. Occupancy certificate

When construction is complete, the owner applies for an occupancy certificate, which confirms that the building was built as approved and is fit to use. Keep the approved drawings and site inspection records ready for this step.

BNBC 2020 in brief

The Bangladesh National Building Code 2020 was published in the official gazette on 11 February 2021 and applies to building construction across the country. It sets standards for planning, structure, fire safety, building services and construction practice, defines a multi-storey building as one of ten storeys or 33 metres and above, and names the Bangladesh Building Regulatory Authority as the body that enforces the code.

What changed in 2025 and 2026

The Dhaka Metropolitan Building Rules 2025 (S.R.O. 469) were gazetted on 14 December 2025 and replace the 2008 rules. They rename the first approval (planning permit instead of land use clearance), are aligned with BNBC 2020 and run through RAJUK's online ECPS system. The Detailed Area Plan for Dhaka (DAP 2022 to 2035) was amended in December 2025, raising the permitted floor area ratio in many areas (for example from 2.75 to 3.25 for residential plots on 6-metre roads), and amended again in October 2026, which added extra FAR for larger residential plots in Purbachal and Jhilmil. Ask your architect to check which DAP amendment and building rules apply to your plot before design starts, because FAR and height limits decide how much you can build.

Tips to avoid delays

How Sthapatto Angon helps

Approval drawings are part of our design work. We check what your plot allows, design within the rules, coordinate the architecture with structural and MEP engineering to BNBC 2020, and prepare the drawings and documents the authority asks for. We have designed buildings in Dhaka, Gazipur, Chattogram, Mongla, Feni and other districts, and inside BEPZA zones. Read how we work or our FAQ.

Call +880 1823-017070 or email sthapatto@gmail.com to discuss your plot.

Sources

This guide is general information, not legal advice.