Building a Factory in a Bangladesh EPZ or Economic Zone: Design and Approvals (2026)
By the Sthapatto Angon design team, Dhaka. Updated October 2026.
Short answer: inside an export processing zone (EPZ), BEPZA allots the plot, approves your building drawings and connects utilities; its citizen's charter sets 15 days for approving an investor's drawings. Economic zones now come under Invest Bangladesh, the agency that absorbed BEZA in August 2026. In every zone the building must still meet the Bangladesh National Building Code (BNBC 2020), and a factory needs fire safety plan approval and environmental clearance.
EPZ, economic zone or private zone?
BEPZA export processing zones: eight zones are in operation (Chattogram, Dhaka, Mongla, Ishwardi, Cumilla, Uttara, Adamjee and Karnaphuli), plus the BEPZA Economic Zone at Mirsharai. Patuakhali and Jashore EPZs are being developed. In FY2026, 566 BEPZA enterprises (451 operating, 115 under implementation) exported US$8.41 billion, 17.51% of Bangladesh's exports.
Economic zones: by 2025 the government had approved 63 government and 24 private economic zones. The largest is the National Special Economic Zone (33,805 acres) across Mirsharai, Sitakunda and Sonagazi, renamed from Bangabandhu Sheikh Mujib Shilpa Nagar in November 2024. The Bangladesh Special Economic Zone at Araihazar, Narayanganj, was the first designed and developed by Japanese companies.
Private zones, such as the Korean EPZ in Anwara, are run by their developers, who set their own plot and building rules within the law.
Who approves what in 2026
Plot and building drawings: BEPZA inside its EPZs; Invest Bangladesh inside government economic zones (BEZA's one-stop service already covered approval of building use and building design); the developer inside a private zone.
Investment services: Invest Bangladesh began work in August 2026 under the Invest Bangladesh Act 2026, merging BIDA, BEZA and the Public-Private Partnership Authority. Its BanglaBiz platform is the single digital window for approvals, registrations and licences.
Fire safety: the Fire Service and Civil Defence approves a factory's fire safety plan before it is set up and issues a fire safety effectiveness certificate after inspection. Operating without a valid certificate breaks the Fire Prevention and Extinguishing Act 2003.
Environment: clearance from the Department of Environment, by industry category under the Environment Conservation Rules 2023. Ask the zone authority which route applies to your project.
Design steps that save months
Read the zone's building rules first. BEPZA publishes its requirements for investors' self-constructed buildings; economic zones and private zones have their own plot and setback rules.
Survey the plot and test the soil. Many zones are on filled or coastal land, so foundations depend on a proper soil test.
Plan around production and safety. Lay out the production flow, truck yards, fire engine access, utilities and future expansion together, and keep the required spacing between buildings. When a fire hit Chattogram EPZ in 2025, officials said several older buildings lacked the required spacing.
Design structure, fire protection and MEP as one set. Coordinated drawings pass review faster than drawings patched after comments. See our factory fire safety guide.
Submit in parallel. File drawings with the zone authority while the fire safety plan and environmental clearance are processed.
Supervise construction and close out. Inspections, the fire safety effectiveness certificate and utility connections come before production starts.
Fire safety in zones is often the bottleneck
In November 2025 the Fire Service found that only 55 of 164 factories in Chattogram EPZ held a valid fire safety certificate, and that many buildings put up before 2008 had been built without following the fire code. Designing the fire safety plan into a new factory from the first layout is far cheaper than retrofitting it later.
Our experience in zones
BEPZA Economic Zone, Mirsharai: the 1,138-acre master plan, a 100-bed hospital, an investor club and hotel, and interiors.
Mongla EPZ: a mosque for about 5,000 worshippers and the Investor Club.
Korean EPZ, Anwara: the Design Development Center (210,000 sq ft, completed 2019) and a residential building.
See our industrial projects, our factory planning guide and our page for international clients.
Planning a factory in a zone?
Call +880 1823-017070 or email sthapatto@gmail.com with the zone, plot size and what you plan to produce. Start your project.
Sources
The Daily Star: Invest Bangladesh begins operations (23 August 2026)
The Daily Star: CEPZ factories and fire safety certificates (10 November 2025)