Building a Factory in a Bangladesh EPZ or Economic Zone: Design and Approvals (2026)

By the Sthapatto Angon design team, Dhaka. Updated October 2026.

Short answer: inside an export processing zone (EPZ), BEPZA allots the plot, approves your building drawings and connects utilities; its citizen's charter sets 15 days for approving an investor's drawings. Economic zones now come under Invest Bangladesh, the agency that absorbed BEZA in August 2026. In every zone the building must still meet the Bangladesh National Building Code (BNBC 2020), and a factory needs fire safety plan approval and environmental clearance.

EPZ, economic zone or private zone?

Who approves what in 2026

Design steps that save months

Fire safety in zones is often the bottleneck

In November 2025 the Fire Service found that only 55 of 164 factories in Chattogram EPZ held a valid fire safety certificate, and that many buildings put up before 2008 had been built without following the fire code. Designing the fire safety plan into a new factory from the first layout is far cheaper than retrofitting it later.

Our experience in zones

See our industrial projects, our factory planning guide and our page for international clients.

Planning a factory in a zone?

Call +880 1823-017070 or email sthapatto@gmail.com with the zone, plot size and what you plan to produce. Start your project.